Bid calculators / Holdback calculator

Holdback calculator

On construction and improvement work, the buyer keeps a share of every payment until the work is done and the lien period has passed. Plan your cash flow around it.

Paid on each invoice$11,250
Held back each time$1,250
Waiting for release$7,500

Over 6 invoices you bill $75,000 and wait for $7,500 of it.

Runs in your browser. Nothing you type is sent anywhere or saved.

How holdback works in BC

Under BC's Builders Lien Act the holdback is 10 percent, kept until 55 days after the work is certified complete or finished. Service contracts such as cleaning or grounds care usually have no holdback, but contracts that improve land or buildings often do. The tender or contract says which applies, and any extra retention on top of it.

Ask when the holdback is released and how, and put the date in your calendar: it's your money, and it's easy to forget.